Land to the North of Cuckoo Grove Farm, Cuckoo Lane, Haverfordwest, SA61 2UY, Dyfed, SA61 2UY
Cuckoo Grove Farm is a 6.1 MW solar farm project in Wales. The applicant or operator on record is Foresight. It is recorded as operational since March 2015. The determining authority is Pembrokeshire, reference 12/0744/PA.β¦
OperationalΒ· Since 2015
Project stageOperating
PlanningNov 2012 (completed)
ConsentedApr 2013 (completed)
ConstructionJan 2015 (completed)
OperatingMar 2015 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2018-09-04.
Registered planning capacity; not measured generation.
Cuckoo Grove Farm is a 6.1 MW solar farm project in Wales. The applicant or operator on record is Foresight. It is recorded as operational since March 2015. The determining authority is Pembrokeshire, reference 12/0744/PA.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
6.100 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Foresight
Owner / operator
Foresight
Year consented
2013
Construction started
2015
Commissioned / target
2015
Location
Land to the North of Cuckoo Grove Farm, Cuckoo Lane, Haverfordwest, SA61 2UY, Dyfed, SA61 2UY