Church Farm, Church Lane, Croydon, Royston, Hertfordshire, Cambridgeshire, SG8 0DL
Croydon / Church Farm (Royston) is a 16.5 MW solar farm project in Eastern. The applicant or operator on record is Push Energy/ NextEnergy Solar Fund (NESF). It is recorded as operational since March 2015. The determining authority is South Cambridgeshire, reference S/2293/13/FL.β¦
OperationalΒ· Since 2015
Project stageOperating
PlanningOct 2013 (completed)
ConsentedAug 2014 (completed)
ConstructionJan 2015 (completed)
OperatingMar 2015 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2015-04-27.
Registered planning capacity; not measured generation.
Croydon / Church Farm (Royston) is a 16.5 MW solar farm project in Eastern. The applicant or operator on record is Push Energy/ NextEnergy Solar Fund (NESF). It is recorded as operational since March 2015. The determining authority is South Cambridgeshire, reference S/2293/13/FL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
16.500 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Push Energy/ NextEnergy Solar Fund (NESF)
Owner / operator
Push Energy/ NextEnergy Solar Fund (NESF)
Year consented
2014
Construction started
2015
Commissioned / target
2015
Location