Park Farm, Dunton Road, Brentwood, Essex, CM13 3SG
Crouch Solar Farm is a 49.9 MW solar farm project in Eastern. The applicant or operator on record is Low Carbon Storage. It is recorded as operational since October 2024. The determining authority is Brentwood, reference 21/00834/FUL.β¦
OperationalΒ· Since 2024
Project stageOperating
PlanningMay 2021 (completed)
ConsentedDec 2021 (completed)
ConstructionJul 2023 (completed)
OperatingOct 2024 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2024-10-30.
Registered planning capacity; not measured generation.
Crouch Solar Farm is a 49.9 MW solar farm project in Eastern. The applicant or operator on record is Low Carbon Storage. It is recorded as operational since October 2024. The determining authority is Brentwood, reference 21/00834/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
49.900 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Low Carbon Storage
Owner / operator
Low Carbon Storage
Year consented
2021
Construction started
2023
Commissioned / target
2024
Location
Park Farm, Dunton Road, Brentwood, Essex, CM13 3SG