π Project Overview
Crossness Sewage Works Turbine is a 2.5 MW onshore wind project in London. The applicant or operator on record is Thames Water Utilities. It is recorded as operational since February 2014. The determining authority is Bexley, reference 08/03936/FULMIN.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
| Capacity (MW) | 3 MW |
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | Thames Water Utilities |
| Owner / operator | Thames Water Utilities |
| Year consented | 2010 |
| Construction started | 2013 |
| Commissioned / target | 2014 |
| Location | Belvedere Road, London, London, SE2 9AR |
| Region | London |
| Coordinates | 51.5021677Β°N, 0.1421258Β°E |