πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Onshore Wind

Crockagarron Ext

Lands to the East of Whitebridge Road and South of Gleneeny Road, on lands at Crockagarron in the Townland of Gleneeny, Co Tyrone., Co. Tyrone

Crockagarron Ext is a 2.5 MW onshore wind project in Northern Ireland. The applicant or operator on record is Northern Wind Power. It is recorded as operational since June 2012. The determining authority is Fermanagh and Omagh, reference K/2009/0182/F.…

Operational Β· Since 2012
Project stageOperating
  1. PlanningMar 2009 (completed)
  2. ConsentedDec 2010 (completed)
  3. ConstructionApr 2012 (completed)
  4. OperatingJun 2012 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2012-12-03.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.500 MW
Registered Capacity
2012
Commissioned

πŸ“‹ Project Overview

Crockagarron Ext is a 2.5 MW onshore wind project in Northern Ireland. The applicant or operator on record is Northern Wind Power. It is recorded as operational since June 2012. The determining authority is Fermanagh and Omagh, reference K/2009/0182/F.

Site Schematic

NORTHERN IRELAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)2.500 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperNorthern Wind Power
Owner / operatorNorthern Wind Power
Year consented2010
Construction started2012
Commissioned / target2012
LocationLands to the East of Whitebridge Road and South of Gleneeny Road, on lands at Crockagarron in the Townland of Gleneeny, Co Tyrone., Co. Tyrone
RegionNorthern Ireland
Coordinates54.5515699Β°N, 7.0090235Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)2.5
No. of Turbines1

πŸ“… Project Timeline

2009-03-04
2010-12-08
2012-04-01
2012-06-01