Solar Farm

Crick Road

Land at, Crick Road, Yelvertoft, Northampton, Northamptonshire, Northamptonshire, NN6 6NA

Crick Road is a 49.9 MW solar farm project in East Midlands. The applicant or operator on record is Lightrock Power / Bluefield Solar Income Fund. It is recorded as under construction since October 2022. The determining authority is West Northamptonshire, reference DA/2020/0200.…

Under Construction
Project stageUnder construction
  1. PlanningApr 2020 (completed)
  2. ConsentedNov 2020 (completed)
  3. ConstructionOct 2022 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2023-05-25.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

49.900 MW
Registered Capacity

πŸ“‹ Project Overview

Crick Road is a 49.9 MW solar farm project in East Midlands. The applicant or operator on record is Lightrock Power / Bluefield Solar Income Fund. It is recorded as under construction since October 2022. The determining authority is West Northamptonshire, reference DA/2020/0200.

Site Schematic

SUBSTATION ? ha Β· 49.9 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)49.900 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperLightrock Power / Bluefield Solar Income Fund
Owner / operatorLightrock Power / Bluefield Solar Income Fund
Year consented2020
Construction started2022
LocationLand at, Crick Road, Yelvertoft, Northampton, Northamptonshire, Northamptonshire, NN6 6NA
RegionEast Midlands
Coordinates52.3596096Β°N, 1.1357175Β°W

Additional published register fields

Registered technologySolar Photovoltaics
CfD Allocation RoundAR4
CfD Capacity (MW)49.9
Mounting Type for SolarGround
Solar Site Area (sqm)808600

πŸ“… Project Timeline

2020-04-08
2020-11-19
2022-10-03