Land at, Crick Road, Yelvertoft, Northampton, Northamptonshire, Northamptonshire, NN6 6NA
Crick Road is a 49.9 MW solar farm project in East Midlands. The applicant or operator on record is Lightrock Power / Bluefield Solar Income Fund. It is recorded as under construction since October 2022. The determining authority is West Northamptonshire, reference DA/2020/0200.β¦
Under Construction
Project stageUnder construction
PlanningApr 2020 (completed)
ConsentedNov 2020 (completed)
ConstructionOct 2022 (current stage)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Under Construction.
Official register: July 2026
Recorded status: Under Construction. Source record updated 2023-05-25.
Registered planning capacity; not measured generation.
Crick Road is a 49.9 MW solar farm project in East Midlands. The applicant or operator on record is Lightrock Power / Bluefield Solar Income Fund. It is recorded as under construction since October 2022. The determining authority is West Northamptonshire, reference DA/2020/0200.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
49.900 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Lightrock Power / Bluefield Solar Income Fund
Owner / operator
Lightrock Power / Bluefield Solar Income Fund
Year consented
2020
Construction started
2022