Solar Farm

Creswell Solar Park

Land To The North And, Frithwo, Elmton, South Of Sewage Treatment Plan, Worksop,, Derbyshire, S80 4LT

Creswell Solar Park is a 5 MW solar farm project in East Midlands. The applicant or operator on record is Sovereign Energy Partners. It is recorded as operational since March 2016. The determining authority is Bolsover, reference 15/00173/FUL.…

Operational Β· Since 2016
Project stageOperating
  1. PlanningApr 2015 (completed)
  2. ConsentedJul 2015 (completed)
  3. ConstructionFeb 2016 (completed)
  4. OperatingMar 2016 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2017-01-16.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

5.000 MW
Registered Capacity
2016
Commissioned

πŸ“‹ Project Overview

Creswell Solar Park is a 5 MW solar farm project in East Midlands. The applicant or operator on record is Sovereign Energy Partners. It is recorded as operational since March 2016. The determining authority is Bolsover, reference 15/00173/FUL.

Site Schematic

SUBSTATION ? ha Β· 5 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)5.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperSovereign Energy Partners
Owner / operatorSovereign Energy Partners
Year consented2015
Construction started2016
Commissioned / target2016
LocationLand To The North And, Frithwo, Elmton, South Of Sewage Treatment Plan, Worksop,, Derbyshire, S80 4LT
RegionEast Midlands
Coordinates53.2558087Β°N, 1.2074328Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Are they re-applying (Old REPD Ref) 2207
Solar Site Area (sqm)118000

πŸ“… Project Timeline

2015-04-20
2015-07-03
2016-02-19
2016-03-23