Land To The North And, Frithwo, Elmton, South Of Sewage Treatment Plan, Worksop,, Derbyshire, S80 4LT
Creswell Solar Park is a 5 MW solar farm project in East Midlands. The applicant or operator on record is Sovereign Energy Partners. It is recorded as operational since March 2016. The determining authority is Bolsover, reference 15/00173/FUL.β¦
OperationalΒ· Since 2016
Project stageOperating
PlanningApr 2015 (completed)
ConsentedJul 2015 (completed)
ConstructionFeb 2016 (completed)
OperatingMar 2016 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2017-01-16.
Registered planning capacity; not measured generation.
Creswell Solar Park is a 5 MW solar farm project in East Midlands. The applicant or operator on record is Sovereign Energy Partners. It is recorded as operational since March 2016. The determining authority is Bolsover, reference 15/00173/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
5.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Sovereign Energy Partners
Owner / operator
Sovereign Energy Partners
Year consented
2015
Construction started
2016
Commissioned / target
2016
Location
Land To The North And, Frithwo, Elmton, South Of Sewage Treatment Plan, Worksop,, Derbyshire, S80 4LT