The Ns/O Sewage Treatment Plant, Frithwood Lane, Elmton, Worksop,, Derbyshire
Creswell is a 5 MW solar farm project in East Midlands. The applicant or operator on record is Sovereign Energy Partners/Creswell Solar. The scheme is currently in the planning system, submitted August 2014. The determining authority is Bolsover, reference 14/00349/FUL.β¦
Revised
Project stageSuperseded by a new application
PlanningAug 2014 (completed)
Superseded by a new application (project stopped here)
ConsentedNov 2014 (not reached)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Revised.
Official register: July 2026
Recorded status: Revised. Source record updated 2017-01-16.
Registered planning capacity; not measured generation.
Creswell is a 5 MW solar farm project in East Midlands. The applicant or operator on record is Sovereign Energy Partners/Creswell Solar. The scheme is currently in the planning system, submitted August 2014. The determining authority is Bolsover, reference 14/00349/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
5.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Sovereign Energy Partners/Creswell Solar
Owner / operator
Sovereign Energy Partners/Creswell Solar
Year consented
2014
Location