Battery Storage

Creag Riabhach Wind Farm Extension & Battery Storage

Creag Riabhach Wind Farm, Creag Riabhach, Lairg, Highland, IV27 4AD

Creag Riabhach Wind Farm Extension & Battery Storage is a 37.3 MW battery storage project in Scotland. The applicant or operator on record is Creag Riabhach Wind Farm Limited. Planning permission has been granted as of July 2024 and it is awaiting construction. The determining au…

Consented / Approved
Project stageConsented
  1. PlanningMay 2022 (completed)
  2. ConsentedJul 2024 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2024-07-10.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

37.300 MW
Power Capacity

πŸ“‹ Project Overview

Creag Riabhach Wind Farm Extension & Battery Storage is a 37.3 MW battery storage project in Scotland. The applicant or operator on record is Creag Riabhach Wind Farm Limited. Planning permission has been granted as of July 2024 and it is awaiting construction. The determining authority is Scottish Government (S36), reference ECU00004487.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)37.300 MW
Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperCreag Riabhach Wind Farm Limited
Owner / operatorCreag Riabhach Wind Farm Limited
Year consented2024
LocationCreag Riabhach Wind Farm, Creag Riabhach, Lairg, Highland, IV27 4AD
RegionScotland
Coordinates58.218388Β°N, 4.4917507Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID11376

πŸ“… Project Timeline

2022-05-10
2024-07-05