Crays Hall Farm Church Lane Ramsden Crays Billericay, Essex, CM11 2UN
Crays Hall Farm - Solar Arrays is a 25.6 MW solar farm project in Eastern. The applicant or operator on record is Boom Power Limited. It is recorded as operational since May 2026. The determining authority is Basildon, reference 22/00296/FULL.β¦
OperationalΒ· Since 2026
Project stageOperating
PlanningMar 2022 (completed)
ConsentedAug 2023 (completed)
ConstructionAug 2025 (completed)
OperatingMay 2026 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2026-06-03.
Registered planning capacity; not measured generation.
Crays Hall Farm - Solar Arrays is a 25.6 MW solar farm project in Eastern. The applicant or operator on record is Boom Power Limited. It is recorded as operational since May 2026. The determining authority is Basildon, reference 22/00296/FULL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
25.600 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Boom Power Limited
Owner / operator
Boom Power Limited
Year consented
2023
Construction started
2025
Commissioned / target
2026
Location
Crays Hall Farm Church Lane Ramsden Crays Billericay, Essex, CM11 2UN