πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Cranford

Cranford Landfill Site, Thrapston Lane, Cranford St. John Nr Kettering, Northamptonshire, Northamptonshire

Cranford is a 1.1 MW bioenergy / waste project in East Midlands. The applicant or operator on record is SITA UK. It is recorded as operational since December 2006. The determining authority is North Northamptonshire, reference KET/2006/0301.…

Operational Β· Since 2006
Project stageOperating
  1. PlanningMar 2006 (completed)
  2. ConsentedApr 2006 (completed)
  3. Construction (completed)
  4. OperatingDec 2006 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2009-10-07.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.100 MW
Registered Capacity
2006
Commissioned

πŸ“‹ Project Overview

Cranford is a 1.1 MW bioenergy / waste project in East Midlands. The applicant or operator on record is SITA UK. It is recorded as operational since December 2006. The determining authority is North Northamptonshire, reference KET/2006/0301.

πŸ”§ Technical Specifications

Capacity (MW)1.100 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperSITA UK
Owner / operatorSITA UK
Year consented2006
Commissioned / target2006
LocationCranford Landfill Site, Thrapston Lane, Cranford St. John Nr Kettering, Northamptonshire, Northamptonshire
RegionEast Midlands
Coordinates52.375939Β°N, 0.6338025Β°W

Additional published register fields

Registered technologyLandfill Gas

πŸ“… Project Timeline

2006-03-29
2006-04-19
2006-12-01