Under Construction
Project stageUnder construction
  1. PlanningNov 2023 (completed)
  2. ConsentedFeb 2024 (completed)
  3. ConstructionAug 2024 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2024-09-24.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

50.000 MW
Power Capacity

πŸ“‹ Project Overview

Coylton Substation, Coylton - Battery Energy Storage is a 50 MW battery storage project in Scotland. The applicant or operator on record is Statkraft UK Limited. It is recorded as under construction since August 2024. The determining authority is East Ayrshire, reference 23/0580/PP.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)50.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperStatkraft UK Limited
Owner / operatorStatkraft UK Limited
Year consented2024
Construction started2024
LocationS/O A70 Adj Coylton Substation, Coylton, Cumnock, Ayrshire, KA18 2RN
RegionScotland
Coordinates55.4463103Β°N, 4.4284305Β°W

Additional published register fields

Registered technologyBattery
Are they re-applying (Old REPD Ref) 10162

πŸ“… Project Timeline

2023-11-03
2024-02-29
2024-08-01