Cowley Main Sub Station, Lower Blackberry Lane, Garsington, Oxford, Oxfordshire, OX44 9BD
Cowley electricity sub-station is a 49.9 MW battery storage project in South East. The applicant or operator on record is Pivot Power. It is recorded as operational since June 2021. The determining authority is South Oxfordshire, reference P19/S0623/FUL.β¦
OperationalΒ· Since 2021
Project stageOperating
PlanningFeb 2019 (completed)
ConsentedJun 2019 (completed)
ConstructionNov 2019 (completed)
OperatingJun 2021 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2026-03-09.
Registered planning capacity; not measured generation.
Cowley electricity sub-station is a 49.9 MW battery storage project in South East. The applicant or operator on record is Pivot Power. It is recorded as operational since June 2021. The determining authority is South Oxfordshire, reference P19/S0623/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
49.900 MW
Battery chemistry
Co-located with fossil fuel plant
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Pivot Power
Owner / operator
Pivot Power
Year consented
2019
Construction started
2019
Commissioned / target
2021
Location
Cowley Main Sub Station, Lower Blackberry Lane, Garsington, Oxford, Oxfordshire, OX44 9BD