County Lane - Solar farm is a 16 MW solar farm project in West Midlands. The applicant or operator on record is Boultbee Brooks Renewable Energy Limited. Planning permission has been granted as of March 2023 and it is awaiting construction. The determining authority is Shropshire…

Consented / Approved
Project stageConsented
  1. PlanningApr 2022 (completed)
  2. ConsentedMar 2023 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2026-02-16.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

16.000 MW
Registered Capacity

πŸ“‹ Project Overview

County Lane - Solar farm is a 16 MW solar farm project in West Midlands. The applicant or operator on record is Boultbee Brooks Renewable Energy Limited. Planning permission has been granted as of March 2023 and it is awaiting construction. The determining authority is Shropshire, reference 22/01816/FUL.

Site Schematic

SUBSTATION ? ha Β· 16 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)16.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperBoultbee Brooks Renewable Energy Limited
Owner / operatorBoultbee Brooks Renewable Energy Limited
Year consented2023
LocationThe W/O County Lane, Albrighton, Wolverhampton, West Midlands, WV8 1RH
RegionWest Midlands
Coordinates52.6346572Β°N, 2.2450608Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Storage Co-location REPD Ref ID11166
CfD Allocation RoundAR7a
CfD Capacity (MW)9
Mounting Type for SolarGround
Solar Site Area (sqm)303600

πŸ“… Project Timeline

2022-04-14
2023-03-21