Staff Car Park County Hall, Loansdean, Morpeth, Northumberland, NE61 2EF

County Hall, Loansdean - Battery Storage is a 0.4 MW battery storage project in North East. The applicant or operator on record is Northumberland County Council. It is recorded as operational since August 2023. The determining authority is Northumberland, reference 22/04405/CCD.…

Operational Β· Since 2023
Project stageOperating
  1. PlanningDec 2022 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingAug 2023 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2023-08-21.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

0.400 MW
Power Capacity
2023
Commissioned

πŸ“‹ Project Overview

County Hall, Loansdean - Battery Storage is a 0.4 MW battery storage project in North East. The applicant or operator on record is Northumberland County Council. It is recorded as operational since August 2023. The determining authority is Northumberland, reference 22/04405/CCD.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)0.400 MW
Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperNorthumberland County Council
Owner / operatorNorthumberland County Council
Commissioned / target2023
LocationStaff Car Park County Hall, Loansdean, Morpeth, Northumberland, NE61 2EF
RegionNorth East
Coordinates55.1533421Β°N, 1.6824242Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID12934
Mounting Type for SolarGround

πŸ“… Project Timeline

2022-12-12
2023-08-18