Land to the North of Hallought, Cotmoor Lane, Southwell,, Nottinghamshire, NG25 0QS
Cotmoor Solar Farm is a battery storage project in East Midlands. The applicant or operator on record is JBM Solar Projects. Planning permission has been granted as of February 2022 and it is awaiting construction. The determining authority is Newark and Sherwood, reference 20/01β¦
Consented / Approved
Project stageConsented
PlanningJul 2020 (completed)
ConsentedFeb 2022 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Appeal Granted.
Official register: July 2026
Recorded status: Appeal Granted. Source record updated 2020-09-30.
Registered planning capacity; not measured generation.
Cotmoor Solar Farm is a battery storage project in East Midlands. The applicant or operator on record is JBM Solar Projects. Planning permission has been granted as of February 2022 and it is awaiting construction. The determining authority is Newark and Sherwood, reference 20/01242/FULM.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Battery chemistry
Co-located with RE
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
JBM Solar Projects
Owner / operator
JBM Solar Projects
Year consented
2022
Location