πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Onshore Wind

Corriegarth 2

Corriegarth Wind Farm, Off B852, Highland, IV2

Corriegarth 2 is a 67.2 MW onshore wind project in Scotland. The applicant or operator on record is Corriegarth 2 Windfarm Limited (BayWa r.e. UK Limited). Planning permission has been granted as of December 2023 and it is awaiting construction. The determining authority is Scott…

Consented / Approved
Project stageConsented
  1. PlanningJan 2021 (completed)
  2. ConsentedDec 2023 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2024-01-02.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

67.200 MW
Registered Capacity

πŸ“‹ Project Overview

Corriegarth 2 is a 67.2 MW onshore wind project in Scotland. The applicant or operator on record is Corriegarth 2 Windfarm Limited (BayWa r.e. UK Limited). Planning permission has been granted as of December 2023 and it is awaiting construction. The determining authority is Scottish Government (S36), reference ECU00002175.

Site Schematic

SCOTLAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)67.200 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperCorriegarth 2 Windfarm Limited (BayWa r.e. UK Limited)
Owner / operatorCorriegarth 2 Windfarm Limited (BayWa r.e. UK Limited)
Year consented2023
LocationCorriegarth Wind Farm, Off B852, Highland, IV2
RegionScotland
Coordinates57.3864996Β°N, 4.2361058Β°W

Additional published register fields

Registered technologyWind Onshore
CfD Allocation RoundAR6
CfD Capacity (MW)66.19
No. of Turbines14
Height of Turbines (m)149.9

πŸ“… Project Timeline

2021-01-18
2023-12-20