Corporation Farm is a 5 MW solar farm project in Eastern. The applicant or operator on record is Lightsource Renewable Energy. The application has been withdrawn or the scheme abandoned. The determining authority is Maldon, reference 15/00779/FUL.…

Withdrawn
Project stageWithdrawn / abandoned
  1. PlanningAug 2015 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedApr 2017 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Abandoned.

Official register: July 2026

Recorded status: Abandoned. Source record updated 2019-03-01.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

5.000 MW
Registered Capacity

πŸ“‹ Project Overview

Corporation Farm is a 5 MW solar farm project in Eastern. The applicant or operator on record is Lightsource Renewable Energy. The application has been withdrawn or the scheme abandoned. The determining authority is Maldon, reference 15/00779/FUL.

Site Schematic

SUBSTATION ? ha Β· 5 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)5.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperLightsource Renewable Energy
Owner / operatorLightsource Renewable Energy
Year consented2017
LocationCorporation Farm, Hackmans Lane, Purleigh, Chelmsford, Essex, CM3 6RH
RegionEastern
Coordinates51.6889874Β°N, 0.6264579Β°E

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround

πŸ“… Project Timeline

2015-08-05
2017-04-25