Corkey Windfarm (repowering)

Corkey Windfarm, Corkey Road, Approx 19km North of Ballymena, Ballymena,, Co. Antrim, BT44 9JB

Corkey Windfarm (repowering) is a 20 MW onshore wind project in Northern Ireland. The applicant or operator on record is ScottishPower Renewables. Planning permission has been granted as of March 2022 and it is awaiting construction. The determining authority is Causeway Coast an…

Consented / Approved
Project stageConsented
  1. PlanningJul 2019 (completed)
  2. ConsentedMar 2022 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2022-03-09.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

20.000 MW
Registered Capacity

πŸ“‹ Project Overview

Corkey Windfarm (repowering) is a 20 MW onshore wind project in Northern Ireland. The applicant or operator on record is ScottishPower Renewables. Planning permission has been granted as of March 2022 and it is awaiting construction. The determining authority is Causeway Coast and Glens, reference LA01/2019/0772/F.

Site Schematic

NORTHERN IRELAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)20.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperScottishPower Renewables
Owner / operatorScottishPower Renewables
Year consented2022
LocationCorkey Windfarm, Corkey Road, Approx 19km North of Ballymena, Ballymena,, Co. Antrim, BT44 9JB
RegionNorthern Ireland
Coordinates55.0325753Β°N, 6.2629122Β°W

Additional published register fields

Registered technologyWind Onshore
No. of Turbines5
Height of Turbines (m)137

πŸ“… Project Timeline

2019-07-09