πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Onshore Wind

Corby Knowe

Tardee Mountain, 7km North East of Antrim and 4km South East of Kells, Co. Antrim

Corby Knowe is a 5 MW onshore wind project in Northern Ireland. The applicant or operator on record is Gaelectric Developments/ CGN Europe Energy. It is recorded as operational since May 2017. The determining authority is Antrim and Newtownabbey, reference T/2006/0832/F.…

Operational Β· Since 2017
Project stageOperating
  1. PlanningNov 2006 (completed)
  2. ConsentedJan 2013 (completed)
  3. ConstructionJan 2016 (completed)
  4. OperatingMay 2017 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2017-05-31.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

5.000 MW
Registered Capacity
2017
Commissioned

πŸ“‹ Project Overview

Corby Knowe is a 5 MW onshore wind project in Northern Ireland. The applicant or operator on record is Gaelectric Developments/ CGN Europe Energy. It is recorded as operational since May 2017. The determining authority is Antrim and Newtownabbey, reference T/2006/0832/F.

Site Schematic

NORTHERN IRELAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)5.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperGaelectric Developments/ CGN Europe Energy
Owner / operatorGaelectric Developments/ CGN Europe Energy
Year consented2013
Construction started2016
Commissioned / target2017
LocationTardee Mountain, 7km North East of Antrim and 4km South East of Kells, Co. Antrim
RegionNorthern Ireland
Coordinates54.790191Β°N, 6.1778055Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)1.6
No. of Turbines3

πŸ“… Project Timeline

2006-11-17
2013-01-30
2016-01-04
2017-05-31