Land east of Cound Brook, Gree, Green Farm, Condover, Shrewsbury, Shropshire, SY5 7DA, Shropshire, SY5 7DA
Condover (Green Farm) is a 10.2 MW solar farm project in West Midlands. The applicant or operator on record is NextEnergy Solar Fund. It is recorded as operational since March 2015. The determining authority is Shropshire, reference 13/03519/FUL.β¦
OperationalΒ· Since 2015
Project stageOperating
PlanningSep 2013 (completed)
ConsentedJan 2014 (completed)
ConstructionNov 2014 (completed)
OperatingMar 2015 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2015-04-20.
Registered planning capacity; not measured generation.
Condover (Green Farm) is a 10.2 MW solar farm project in West Midlands. The applicant or operator on record is NextEnergy Solar Fund. It is recorded as operational since March 2015. The determining authority is Shropshire, reference 13/03519/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
10.200 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
NextEnergy Solar Fund
Owner / operator
NextEnergy Solar Fund
Year consented
2014
Construction started
2014
Commissioned / target
2015
Location
Land east of Cound Brook, Gree, Green Farm, Condover, Shrewsbury, Shropshire, SY5 7DA, Shropshire, SY5 7DA