Solar Farm

Cobbs Cross Solar Park

S/O Durleigh Hill, Bridgwater, Somerset, Somerset, TA5 2AG

Cobbs Cross Solar Park is a 5 MW solar farm project in South West. The applicant or operator on record is PS Renewables. It is recorded as operational since March 2013. The determining authority is Somerset, reference 23/12/00005.…

Operational Β· Since 2013
Project stageOperating
  1. PlanningMay 2012 (completed)
  2. ConsentedSep 2012 (completed)
  3. Construction (completed)
  4. OperatingMar 2013 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2013-10-07.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

5.000 MW
Registered Capacity
2013
Commissioned

πŸ“‹ Project Overview

Cobbs Cross Solar Park is a 5 MW solar farm project in South West. The applicant or operator on record is PS Renewables. It is recorded as operational since March 2013. The determining authority is Somerset, reference 23/12/00005.

Site Schematic

SUBSTATION ? ha Β· 5 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)5.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperPS Renewables
Owner / operatorPS Renewables
Year consented2012
Commissioned / target2013
LocationS/O Durleigh Hill, Bridgwater, Somerset, Somerset, TA5 2AG
RegionSouth West
Coordinates51.1123878Β°N, 3.0370749Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)156000

πŸ“… Project Timeline

2012-05-28
2012-09-20
2013-03-30