πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Onshore Wind

Cnoc Donn Arnicle

Situated next to Beinn an Tuirc Kintyre, Strathclyde

Cnoc Donn Arnicle is a 15 MW onshore wind project in Scotland. The applicant or operator on record is CRE Energy/ Scottish Power. It is recorded as operational since October 2001. The determining authority is Argyll and Bute.…

Operational Β· Since 2001
Project stageOperating
  1. PlanningApr 1998 (completed)
  2. ConsentedApr 1999 (completed)
  3. Construction (completed)
  4. OperatingOct 2001 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2010-02-03.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

15.000 MW
Registered Capacity
2001
Commissioned

πŸ“‹ Project Overview

Cnoc Donn Arnicle is a 15 MW onshore wind project in Scotland. The applicant or operator on record is CRE Energy/ Scottish Power. It is recorded as operational since October 2001. The determining authority is Argyll and Bute.

Site Schematic

SCOTLAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)15.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperCRE Energy/ Scottish Power
Owner / operatorCRE Energy/ Scottish Power
Year consented1999
Commissioned / target2001
LocationSituated next to Beinn an Tuirc Kintyre, Strathclyde
RegionScotland
Coordinates55.5800263Β°N, 5.5681373Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)0.57
No. of Turbines26

πŸ“… Project Timeline

1998-04-20
1999-04-28
2001-10-01