Onshore Wind

Cloonty Wind Farm

122 Castlecat Road Derry Keighan, Cloonty Townland, Ballymoney, Co Antrim. BT53 8AP, Co. Antrim

Cloonty Wind Farm is a 12 MW onshore wind project in Northern Ireland. The applicant or operator on record is Gaelectric Developments/ CGN Europe Energy. It is recorded as operational since August 2016. The determining authority is Causeway Coast and Glens, reference D/2009/0142/…

Operational Β· Since 2016
12 MW
Installed Capacity
2016
Commissioned

πŸ“‹ Project Overview

Cloonty Wind Farm is a 12 MW onshore wind project in Northern Ireland. The applicant or operator on record is Gaelectric Developments/ CGN Europe Energy. It is recorded as operational since August 2016. The determining authority is Causeway Coast and Glens, reference D/2009/0142/F.

Site Schematic

NORTHERN IRELAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)12 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperGaelectric Developments/ CGN Europe Energy
Owner / operatorGaelectric Developments/ CGN Europe Energy
Year consented2013
Construction started2015
Commissioned / target2016
Location122 Castlecat Road Derry Keighan, Cloonty Townland, Ballymoney, Co Antrim. BT53 8AP, Co. Antrim
RegionNorthern Ireland
Coordinates55.1184921Β°N, 6.3958217Β°W

πŸ“… Project Timeline