Clifton Marsh Waste Water Treatment Works is a 2 MW battery storage project in North West. The applicant or operator on record is United Utilities. It is recorded as operational since June 2020. The determining authority is Fylde, reference LCC/2019/0045.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
| Capacity (MW) | 2 MW |
| Battery chemistry | Co-located with RE |
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | United Utilities |
| Owner / operator | United Utilities |
| Year consented | 2019 |
| Construction started | 2020 |
| Commissioned / target | 2020 |
| Location | CLIFTON MARSH WASTE WATER TREATMENT WORKS, PRESTON NEW ROAD, FRECKLETON, Lancashire |
| Region | North West |
| Coordinates | 53.7534048Β°N, 2.8262895Β°W |