Clawdd Ddu PV is a 13.5 MW solar farm project in Wales. The applicant or operator on record is Elgin Energy EsCo. It is recorded as operational since March 2014. The determining authority is Carmarthenshire, reference S/27987.…

Operational Β· Since 2014
Project stageOperating
  1. PlanningMar 2013 (completed)
  2. ConsentedOct 2013 (completed)
  3. Construction (completed)
  4. OperatingMar 2014 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2014-08-26.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

13.500 MW
Registered Capacity
2014
Commissioned

πŸ“‹ Project Overview

Clawdd Ddu PV is a 13.5 MW solar farm project in Wales. The applicant or operator on record is Elgin Energy EsCo. It is recorded as operational since March 2014. The determining authority is Carmarthenshire, reference S/27987.

Site Schematic

SUBSTATION ? ha Β· 13.5 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)13.500 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperElgin Energy EsCo
Owner / operatorElgin Energy EsCo
Year consented2013
Commissioned / target2014
LocationPotardulas Road, Tycroes, Swansea, Dyfed, SA18 3RE
RegionWales
Coordinates51.7708136Β°N, 4.0380486Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround

πŸ“… Project Timeline

2013-03-27
2013-10-07
2014-03-26