Onshore Wind

Clashindarroch 2

Clashindarroch Forest, Huntly,, Grampian

Clashindarroch 2 is a 77 MW onshore wind project in Scotland. The applicant or operator on record is Vattenfall. Planning permission has been granted as of August 2023 and it is awaiting construction. The determining authority is Scottish Government (S36), reference ECU00002002.…

Consented / Approved
Project stageConsented
  1. PlanningDec 2019 (completed)
  2. ConsentedAug 2023 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Appeal Granted.

Official register: July 2026

Recorded status: Appeal Granted. Source record updated 2023-06-28.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

77.000 MW
Registered Capacity

πŸ“‹ Project Overview

Clashindarroch 2 is a 77 MW onshore wind project in Scotland. The applicant or operator on record is Vattenfall. Planning permission has been granted as of August 2023 and it is awaiting construction. The determining authority is Scottish Government (S36), reference ECU00002002.

Site Schematic

SCOTLAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)77.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperVattenfall
Owner / operatorVattenfall
Year consented2023
LocationClashindarroch Forest, Huntly,, Grampian
RegionScotland
Coordinates57.3839698Β°N, 2.9330942Β°W

Additional published register fields

Registered technologyWind Onshore
CfD Allocation RoundAR6
CfD Capacity (MW)77
Turbine Capacity (MW)6
No. of Turbines14
Height of Turbines (m)180

πŸ“… Project Timeline

2019-12-23
2023-08-11