located to the southwest, north and east of Berry Burn, Moray
Clash Gour is a 50 MW battery storage project in Scotland. The applicant or operator on record is EDF Energy Renewables/ Force 9. Planning permission has been granted as of October 2022 and it is awaiting construction. The determining authority is Scottish Government (S36), referβ¦
Consented / Approved
Project stageConsented
PlanningDec 2018 (completed)
ConsentedOct 2022 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2022-10-27.
Registered planning capacity; not measured generation.
Clash Gour is a 50 MW battery storage project in Scotland. The applicant or operator on record is EDF Energy Renewables/ Force 9. Planning permission has been granted as of October 2022 and it is awaiting construction. The determining authority is Scottish Government (S36), reference ECU00000738.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
50.000 MW
Battery chemistry
Co-located with RE
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
EDF Energy Renewables/ Force 9
Owner / operator
EDF Energy Renewables/ Force 9
Year consented
2022
Location
located to the southwest, north and east of Berry Burn, Moray