Cholmondeley Road - Battery Storage is a 150 MW battery storage project in North West. The applicant or operator on record is P3P Partners LLP. Planning permission has been granted as of August 2022 and it is awaiting construction. The determining authority is Halton, reference 2…

Consented / Approved
Project stageConsented
  1. PlanningSep 2021 (completed)
  2. ConsentedAug 2022 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2026-03-18.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

150.000 MW
Power Capacity

πŸ“‹ Project Overview

Cholmondeley Road - Battery Storage is a 150 MW battery storage project in North West. The applicant or operator on record is P3P Partners LLP. Planning permission has been granted as of August 2022 and it is awaiting construction. The determining authority is Halton, reference 21/00565/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)150.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperP3P Partners LLP
Owner / operatorP3P Partners LLP
Year consented2022
LocationThe South East Of Junction Between Weaver View And Cholmondeley Road Runcorn, Cheshire, WA7 4XU
RegionNorth West
Coordinates53.3136815Β°N, 2.7149382Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2021-09-29