Chesterfield Road, Swallownest, Sheffield, South Yorkshire, S26 4TL
Chesterfield Road, Swallownest - Battery Energy Storage is a battery storage project in Yorkshire and Humber. The applicant or operator on record is Conrad Energy Developments Ii Limited. The scheme is currently in the planning system, submitted September 2023. The determining auβ¦
In Planning
Project stageIn planning
PlanningSep 2023 (current stage)
Consented (not yet reached)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Application Submitted.
Official register: July 2026
Recorded status: Planning Application Submitted. Source record updated 2023-10-12.
Registered planning capacity; not measured generation.
Chesterfield Road, Swallownest - Battery Energy Storage is a battery storage project in Yorkshire and Humber. The applicant or operator on record is Conrad Energy Developments Ii Limited. The scheme is currently in the planning system, submitted September 2023. The determining authority is Rotherham, reference RB2023/1323.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Conrad Energy Developments Ii Limited
Owner / operator
Conrad Energy Developments Ii Limited
Location
Chesterfield Road, Swallownest, Sheffield, South Yorkshire, S26 4TL