Chester Business Park, Lakewood - Solar Panels is a 0.2 MW solar farm project in North West. The applicant or operator on record is Mara Electrical. Planning permission has been granted as of April 2022 and it is awaiting construction. The determining authority is Cheshire West and Chester, reference 22/00886/P14.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
| Capacity (MW) | 0.200 MW |
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | Mara Electrical |
| Owner / operator | Mara Electrical |
| Year consented | 2022 |
| Location | Bristol Myers Squibb Chester Business Park Lakewood, Cheshire, CH4 9QW |
| Region | North West |
| Coordinates | 53.1594862Β°N, 2.9061123Β°W |
Additional published register fields
| Registered technology | Solar Photovoltaics |
|---|---|
| Mounting Type for Solar | Roof |