Chelveston Airfield
East Northamptonshore, Northamptonshire
Chelveston Renewable Energy Park Wind Farm (East Northamptonshire) is a 12.5 MW onshore wind project in East Midlands. The applicant or operator on record is Chelveston Renewable Energy. It is recorded as operational since February 2014. The determining authority is North Northamβ¦
OperationalΒ· Since 2014
Project stageOperating
PlanningMar 2010 (completed)
ConsentedJun 2012 (completed)
ConstructionAug 2013 (completed)
OperatingFeb 2014 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2014-05-06.
Registered planning capacity; not measured generation.
Chelveston Renewable Energy Park Wind Farm (East Northamptonshire) is a 12.5 MW onshore wind project in East Midlands. The applicant or operator on record is Chelveston Renewable Energy. It is recorded as operational since February 2014. The determining authority is North Northamptonshire, reference 10/00415/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
12.500 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Chelveston Renewable Energy
Owner / operator
Chelveston Renewable Energy
Year consented
2012
Construction started
2013
Commissioned / target
2014
Location
Chelveston Airfield
East Northamptonshore, Northamptonshire