Chelveston Renewable Energy Park, Caldecott, Wellingborough, Northamptonshire, Northamptonshire, NN9 6AR
Chelveston Renewable Energy Park is a 21 MW solar farm project in East Midlands. The applicant or operator on record is Wykes Engineering. The planning permission has expired. The determining authority is North Northamptonshire, reference 15/00489/FUL.β¦
Expired
Project stageConsent lapsed
PlanningMar 2015 (completed)
ConsentedJun 2015 (completed)
Consent lapsed (project stopped here)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Planning Permission Expired.
Official register: July 2026
Recorded status: Planning Permission Expired. Source record updated 2018-07-19.
Registered planning capacity; not measured generation.
Chelveston Renewable Energy Park is a 21 MW solar farm project in East Midlands. The applicant or operator on record is Wykes Engineering. The planning permission has expired. The determining authority is North Northamptonshire, reference 15/00489/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
21.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Wykes Engineering
Owner / operator
Wykes Engineering
Year consented
2015
Location