Chelker Reservoir, Addingham, Ilkley, West Yorkshire, North Yorkshire
Chelker Reservoir Repower (Resubmission) is a 1.7 MW onshore wind project in Yorkshire and Humber. The applicant or operator on record is Kelda Water Services. The planning application was refused. The determining authority is North Yorkshire, reference 24/2011/12076.β¦
Refused
Project stageRefused
PlanningOct 2011 (completed)
Refused (project stopped here)
Consented (not reached)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Planning Permission Refused.
Official register: July 2026
Recorded status: Planning Permission Refused. Source record updated 2012-03-29.
Registered planning capacity; not measured generation.
Chelker Reservoir Repower (Resubmission) is a 1.7 MW onshore wind project in Yorkshire and Humber. The applicant or operator on record is Kelda Water Services. The planning application was refused. The determining authority is North Yorkshire, reference 24/2011/12076.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
1.700 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Kelda Water Services
Owner / operator
Kelda Water Services
Location
Chelker Reservoir, Addingham, Ilkley, West Yorkshire, North Yorkshire