Land adjacent to Chelker Reservoir, nr Skipton, North Yorkshire
Chelker Reservoir is a 1.3 MW onshore wind project in Yorkshire and Humber. The applicant or operator on record is Yorkshire Water. It is recorded as operational since June 1992. The determining authority is North Yorkshire, reference 5/24/96/A/EA.β¦
OperationalΒ· Since 1992
Project stageOperating
Planning (completed)
ConsentedJul 1991 (completed)
Construction (completed)
OperatingJun 1992 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2009-07-06.
Registered planning capacity; not measured generation.
Chelker Reservoir is a 1.3 MW onshore wind project in Yorkshire and Humber. The applicant or operator on record is Yorkshire Water. It is recorded as operational since June 1992. The determining authority is North Yorkshire, reference 5/24/96/A/EA.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
1.300 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Yorkshire Water
Owner / operator
Yorkshire Water
Year consented
1991
Commissioned / target
1992
Location
Land adjacent to Chelker Reservoir, nr Skipton, North Yorkshire