Energy Storage

Cheesecake Energy Air Energy Storage

Nottinghamshire County Council Higways Department, Nottinghamshire, NG22 8ST

Cheesecake Energy Air Energy Storage is an energy storage project in East Midlands. The applicant or operator on record is Via East Midlands Limited. It is recorded as operational since September 2021. The determining authority is Newark and Sherwood, reference 20/02123/FUL.…

Operational Β· Since 2021
Project stageOperating
  1. PlanningNov 2020 (completed)
  2. ConsentedJan 2021 (completed)
  3. Construction (completed)
  4. OperatingSep 2021 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2021-09-25.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2021
Commissioned

πŸ“‹ Project Overview

Cheesecake Energy Air Energy Storage is an energy storage project in East Midlands. The applicant or operator on record is Via East Midlands Limited. It is recorded as operational since September 2021. The determining authority is Newark and Sherwood, reference 20/02123/FUL.

πŸ”§ Technical Specifications

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperVia East Midlands Limited
Owner / operatorVia East Midlands Limited
Year consented2021
Commissioned / target2021
LocationNottinghamshire County Council Higways Department, Nottinghamshire, NG22 8ST
RegionEast Midlands
Coordinates53.1453239Β°N, 1.0267499Β°W

Additional published register fields

Registered technologyCompressed Air Energy Storage

πŸ“… Project Timeline

2020-11-26
2021-01-19
2021-09-25