πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Chapman's Well

Morrison Busty Industrial Estate, Anfield, Durham, County Durham

Chapman's Well is a 1 MW bioenergy / waste project in North East. The applicant or operator on record is Natural Power. It is recorded as operational since March 2003. The determining authority is County Durham, reference CMA/1/8.…

Operational Β· Since 2003
Project stageOperating
  1. PlanningMay 2002 (completed)
  2. ConsentedAug 2002 (completed)
  3. Construction (completed)
  4. OperatingMar 2003 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2010-08-06.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.000 MW
Registered Capacity
2003
Commissioned

πŸ“‹ Project Overview

Chapman's Well is a 1 MW bioenergy / waste project in North East. The applicant or operator on record is Natural Power. It is recorded as operational since March 2003. The determining authority is County Durham, reference CMA/1/8.

πŸ”§ Technical Specifications

Capacity (MW)1.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperNatural Power
Owner / operatorNatural Power
Year consented2002
Commissioned / target2003
LocationMorrison Busty Industrial Estate, Anfield, Durham, County Durham
RegionNorth East
Coordinates54.8518038Β°N, 1.7319717Β°W

Additional published register fields

Registered technologyLandfill Gas

πŸ“… Project Timeline

2002-05-30
2002-08-21
2003-03-01