Adj The Duckery, Chapel Lane, Great Barr, Walsall, West Midlands, WS9 0QU
Chapel Lane - Battery Energy Storage System is a 49.35 MW battery storage project in West Midlands. The applicant or operator on record is Anesco Limited. Planning permission has been granted as of January 2025 and it is awaiting construction. The determining authority is Walsallβ¦
Consented / Approved
Project stageConsented
PlanningOct 2023 (completed)
ConsentedJan 2025 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Appeal Granted.
Official register: July 2026
Recorded status: Appeal Granted. Source record updated 2025-01-21.
Registered planning capacity; not measured generation.
Chapel Lane - Battery Energy Storage System is a 49.35 MW battery storage project in West Midlands. The applicant or operator on record is Anesco Limited. Planning permission has been granted as of January 2025 and it is awaiting construction. The determining authority is Walsall, reference 23/1286.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
49.350 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Anesco Limited
Owner / operator
Anesco Limited
Year consented
2025
Location
Adj The Duckery, Chapel Lane, Great Barr, Walsall, West Midlands, WS9 0QU