Chancery Farm, Park Road, Ardleigh, Colchester, Essex, CO7 7SS
Chancery Farm (Ardleigh) is a 11.9 MW solar farm project in Eastern. The applicant or operator on record is BlackRock. It is recorded as operational since March 2016. The determining authority is Tendring, reference 14/00408/FUL.β¦
OperationalΒ· Since 2016
Project stageOperating
PlanningApr 2014 (completed)
ConsentedDec 2015 (completed)
ConstructionDec 2015 (completed)
OperatingMar 2016 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2017-03-01.
Registered planning capacity; not measured generation.
Chancery Farm (Ardleigh) is a 11.9 MW solar farm project in Eastern. The applicant or operator on record is BlackRock. It is recorded as operational since March 2016. The determining authority is Tendring, reference 14/00408/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
11.900 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
BlackRock
Owner / operator
BlackRock
Year consented
2015
Construction started
2015
Commissioned / target
2016
Location
Chancery Farm, Park Road, Ardleigh, Colchester, Essex, CO7 7SS