N/O Kingsdown Road & West Of Catsbrain Farm Swindon, Wiltshire, SN3 4TD
Catsbrain Farm - Battery Storage is a 30 MW battery storage project in South West. The applicant or operator on record is Conrad Energy (Developments) II Limited. Planning permission has been granted as of October 2023 and it is awaiting construction. The determining authority isβ¦
Consented / Approved
Project stageConsented
PlanningJul 2022 (completed)
ConsentedOct 2023 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2022-08-04.
Registered planning capacity; not measured generation.
Catsbrain Farm - Battery Storage is a 30 MW battery storage project in South West. The applicant or operator on record is Conrad Energy (Developments) II Limited. Planning permission has been granted as of October 2023 and it is awaiting construction. The determining authority is Swindon, reference S/22/1051.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
30.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Conrad Energy (Developments) II Limited
Owner / operator
Conrad Energy (Developments) II Limited
Year consented
2023