Bioenergy / Waste

Castle Farm, Castle Lane - Biomass Boiler & Agricultural Building

Castle Farm, Castle Lane, Lowfields, Navenby, Lincoln, Lincolnshire, LN5 0LL

Castle Farm, Castle Lane - Biomass Boiler & Agricultural Building is a 1.6 MW bioenergy / waste project in East Midlands. The applicant or operator on record is G.E. Porter & Sons Limited. It is recorded as under construction since February 2023. The determining authority is Nort…

Under Construction
Project stageUnder construction
  1. PlanningAug 2022 (completed)
  2. ConsentedJun 2023 (completed)
  3. ConstructionFeb 2023 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2023-03-20.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.600 MW
Registered Capacity

πŸ“‹ Project Overview

Castle Farm, Castle Lane - Biomass Boiler & Agricultural Building is a 1.6 MW bioenergy / waste project in East Midlands. The applicant or operator on record is G.E. Porter & Sons Limited. It is recorded as under construction since February 2023. The determining authority is North Kesteven, reference 22/1200/FUL.

πŸ”§ Technical Specifications

Capacity (MW)1.600 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperG.E. Porter & Sons Limited
Owner / operatorG.E. Porter & Sons Limited
Year consented2023
Construction started2023
LocationCastle Farm, Castle Lane, Lowfields, Navenby, Lincoln, Lincolnshire, LN5 0LL
RegionEast Midlands
Coordinates53.1171956Β°N, 0.572004Β°W

Additional published register fields

Registered technologyBiomass (dedicated)

πŸ“… Project Timeline

2022-08-19
2023-06-06
2023-02-01