Castle Eaton Farm is a 17.8 MW solar farm project in South West. The applicant or operator on record is Hive Energy. It is recorded as operational since March 2014. The determining authority is Swindon, reference S/12/1766.…

Operational Β· Since 2014
Project stageOperating
  1. PlanningDec 2012 (completed)
  2. ConsentedMar 2013 (completed)
  3. Construction (completed)
  4. OperatingMar 2014 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2014-09-02.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

17.800 MW
Registered Capacity
2014
Commissioned

πŸ“‹ Project Overview

Castle Eaton Farm is a 17.8 MW solar farm project in South West. The applicant or operator on record is Hive Energy. It is recorded as operational since March 2014. The determining authority is Swindon, reference S/12/1766.

Site Schematic

SUBSTATION ? ha Β· 17.8 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)17.800 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperHive Energy
Owner / operatorHive Energy
Year consented2013
Commissioned / target2014
LocationMill Lane, Castle Eaton, Swindon, Wiltshire, SN6 6JX
RegionSouth West
Coordinates51.6490633Β°N, 1.7907253Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)403200

πŸ“… Project Timeline

2012-12-11
2013-03-25