Land associated with Castell D, Castell Ddu Road, Pontarddulais, West Glamorgan, SA4 8DH
Castell Ddu Solar Farm is a 5 MW solar farm project in Wales. The applicant or operator on record is Caledon Partners (Solar Power Parks). The planning permission has expired. The determining authority is Swansea, reference 2015/1786.β¦
Expired
Project stageConsent lapsed
PlanningSep 2015 (completed)
ConsentedJan 2016 (completed)
Consent lapsed (project stopped here)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Planning Permission Expired.
Official register: July 2026
Recorded status: Planning Permission Expired. Source record updated 2020-03-18.
Registered planning capacity; not measured generation.
Castell Ddu Solar Farm is a 5 MW solar farm project in Wales. The applicant or operator on record is Caledon Partners (Solar Power Parks). The planning permission has expired. The determining authority is Swansea, reference 2015/1786.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
5.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Caledon Partners (Solar Power Parks)
Owner / operator
Caledon Partners (Solar Power Parks)
Year consented
2016
Location
Land associated with Castell D, Castell Ddu Road, Pontarddulais, West Glamorgan, SA4 8DH