πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Onshore Wind

Carwath Wind Farm

Carwath, Rosley, Wigton, Cumbria CA7 8BW, Cumbria

Carwath Wind Farm is a 7.5 MW onshore wind project in North West. The applicant or operator on record is West Coast Energy/Carwath Farm Wind Energy Ltd. The planning application was refused. The determining authority is Cumberland, reference 2/2013/0227.…

Refused
Project stageRefused
  1. PlanningApr 2013 (completed)
  2. Refused (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Permission Refused.

Official register: July 2026

Recorded status: Planning Permission Refused. Source record updated 2015-03-09.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

7.500 MW
Registered Capacity

πŸ“‹ Project Overview

Carwath Wind Farm is a 7.5 MW onshore wind project in North West. The applicant or operator on record is West Coast Energy/Carwath Farm Wind Energy Ltd. The planning application was refused. The determining authority is Cumberland, reference 2/2013/0227.

Site Schematic

NORTH WEST Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)7.500 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperWest Coast Energy/Carwath Farm Wind Energy Ltd
Owner / operatorWest Coast Energy/Carwath Farm Wind Energy Ltd
LocationCarwath, Rosley, Wigton, Cumbria CA7 8BW, Cumbria
RegionNorth West
Coordinates54.8111886Β°N, 3.0529603Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)2.5
No. of Turbines3

πŸ“… Project Timeline

2013-04-08