Lands north of Slievetrue Road, Carn Hill/Rea Hill, Newtownabbey, Co Antrim, Co. Antrim
Carn Hill is a 13.8 MW onshore wind project in Northern Ireland. The applicant or operator on record is Gaelectric Developments/ CGN Europe Energy. It is recorded as operational since May 2013. The determining authority is Antrim and Newtownabbey, reference U/2006/0054/F.β¦
OperationalΒ· Since 2013
Project stageOperating
PlanningFeb 2006 (completed)
ConsentedFeb 2010 (completed)
ConstructionMay 2012 (completed)
OperatingMay 2013 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2017-01-03.
Registered planning capacity; not measured generation.
Carn Hill is a 13.8 MW onshore wind project in Northern Ireland. The applicant or operator on record is Gaelectric Developments/ CGN Europe Energy. It is recorded as operational since May 2013. The determining authority is Antrim and Newtownabbey, reference U/2006/0054/F.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
13.800 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Gaelectric Developments/ CGN Europe Energy
Owner / operator
Gaelectric Developments/ CGN Europe Energy
Year consented
2010
Construction started
2012
Commissioned / target
2013
Location
Lands north of Slievetrue Road, Carn Hill/Rea Hill, Newtownabbey, Co Antrim, Co. Antrim