πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Candles/Coalmoor Landfill

Dog Lane, New Works, Telford, Shropshire

Candles/Coalmoor Landfill is a 2.9 MW bioenergy / waste project in West Midlands. The applicant or operator on record is ONYX LANDFILL LTD. It is recorded as operational since October 2005. The determining authority is Telford and Wrekin.…

Operational Β· Since 2005
Project stageOperating
  1. PlanningFeb 1999 (completed)
  2. ConsentedSep 2001 (completed)
  3. Construction (completed)
  4. OperatingOct 2005 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2010-06-09.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.900 MW
Registered Capacity
2005
Commissioned

πŸ“‹ Project Overview

Candles/Coalmoor Landfill is a 2.9 MW bioenergy / waste project in West Midlands. The applicant or operator on record is ONYX LANDFILL LTD. It is recorded as operational since October 2005. The determining authority is Telford and Wrekin.

πŸ”§ Technical Specifications

Capacity (MW)2.900 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperONYX LANDFILL LTD
Owner / operatorONYX LANDFILL LTD
Year consented2001
Commissioned / target2005
LocationDog Lane, New Works, Telford, Shropshire
RegionWest Midlands
Coordinates52.6659587Β°N, 2.4997431Β°W

Additional published register fields

Registered technologyLandfill Gas

πŸ“… Project Timeline

1999-02-25
2001-09-01
2005-10-01