Onshore Wind

Camster II

Watten and Lybster, Highland, KW1

Camster II is a 36 MW onshore wind project in Scotland. The applicant or operator on record is E.ON UK. It is recorded as operational since April 2026. The determining authority is Highland, reference 19/03015/FUL.…

Operational Β· Since 2026
Project stageOperating
  1. PlanningAug 2019 (completed)
  2. ConsentedJul 2021 (completed)
  3. ConstructionOct 2023 (completed)
  4. OperatingApr 2026 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2026-05-14.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

36.000 MW
Registered Capacity
2026
Commissioned

πŸ“‹ Project Overview

Camster II is a 36 MW onshore wind project in Scotland. The applicant or operator on record is E.ON UK. It is recorded as operational since April 2026. The determining authority is Highland, reference 19/03015/FUL.

Site Schematic

SCOTLAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)36.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperE.ON UK
Owner / operatorE.ON UK
Year consented2021
Construction started2023
Commissioned / target2026
LocationWatten and Lybster, Highland, KW1
RegionScotland
Coordinates58.4177691Β°N, 3.2205717Β°W

Additional published register fields

Registered technologyWind Onshore
CfD Allocation RoundAR5
CfD Capacity (MW)36
Turbine Capacity (MW)3.6
No. of Turbines10
Height of Turbines (m)127

πŸ“… Project Timeline

2019-08-07
2021-07-28
2023-10-01
2026-04-01