Battery Storage

Camilla Battery Storage

Camilla Farm Auchtertool Kirkcaldy, Fife, KY2 5XW

Camilla Battery Storage is a 49.99 MW battery storage project in Scotland. The applicant or operator on record is NextEnergy Solar Fund / Eelpower Limited. It is recorded as operational since March 2024. The determining authority is Fife, reference 20/01765/ARC.…

Operational Β· Since 2024
Project stageOperating
  1. PlanningAug 2020 (completed)
  2. ConsentedOct 2022 (completed)
  3. ConstructionOct 2023 (completed)
  4. OperatingMar 2024 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2024-03-27.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

49.990 MW
Power Capacity
2024
Commissioned

πŸ“‹ Project Overview

Camilla Battery Storage is a 49.99 MW battery storage project in Scotland. The applicant or operator on record is NextEnergy Solar Fund / Eelpower Limited. It is recorded as operational since March 2024. The determining authority is Fife, reference 20/01765/ARC.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)49.990 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperNextEnergy Solar Fund / Eelpower Limited
Owner / operatorNextEnergy Solar Fund / Eelpower Limited
Year consented2022
Construction started2023
Commissioned / target2024
LocationCamilla Farm Auchtertool Kirkcaldy, Fife, KY2 5XW
RegionScotland
Coordinates56.1089683Β°N, 3.2661649Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2020-08-26
2022-10-22
2023-10-01
2024-03-20