California Farm, Letch Lane, Carlton, Stockton on Tees, Cleveland, TS21 1ED
California Farm - Solar Farm & Battery Storage is a 49.9 MW solar farm project in North East. The applicant or operator on record is Infinis Solar Developments Limited. Planning permission has been granted as of March 2023 and it is awaiting construction. The determining authoritβ¦
Consented / Approved
Project stageConsented
PlanningJun 2022 (completed)
ConsentedMar 2023 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2026-02-16.
Registered planning capacity; not measured generation.
California Farm - Solar Farm & Battery Storage is a 49.9 MW solar farm project in North East. The applicant or operator on record is Infinis Solar Developments Limited. Planning permission has been granted as of March 2023 and it is awaiting construction. The determining authority is Stockton-on-Tees, reference 22/1511/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
49.900 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Infinis Solar Developments Limited
Owner / operator
Infinis Solar Developments Limited
Year consented
2023
Location
California Farm, Letch Lane, Carlton, Stockton on Tees, Cleveland, TS21 1ED