π Project Overview
Caledon Green - Gas Powered Electricity Generation Facility is a 22.5 MW bioenergy / waste project in Scotland. The applicant or operator on record is Claverhouse Generation Limited. Planning permission has been granted as of June 2021 and it is awaiting construction. The determining authority is Falkirk, reference P/21/0062/FUL.
π§ Technical Specifications
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | Claverhouse Generation Limited |
| Owner / operator | Claverhouse Generation Limited |
| Year consented | 2021 |
| Location | Land To South East Of 2 Caledon Green Caledon Green Grangemouth, Stirling, FK3 8TR |
| Region | Scotland |
| Coordinates | 56.0101307Β°N, 3.7406078Β°W |
Additional published register fields
| Registered technology | Landfill Gas |
|---|